Function working now.
Thank you so much.
Good days everyone.
Philip Pai-Pin Chen
nyseasia us; nyseasia NY
nyseasia worldwide.
April 8th.,
2014.
My work with you since
2006.
Thank you so much.
Draft:
Not for construction.
Revided and updated
required-Philip Pai-Pin Chen.
High Rise Commerical Tower
Building(HRCTB)
Date: April 7, 2014 PPC/ADSC
ADSC
From: 陳柏彬 Philip Pai-Pin Chen, Director / NYSEASIA Worldwide
PROPOSAL建議書 DRAFT(Revised and updated
required, Not for construction)
RE: Mechanical ,Electrical & Plumbing Related
Subject: M&E Drawings
Update and Man Power Arrangement
BID DOCUMENTS
AND
PURCHASE SPECIFICATIONS
FOR
Electrical Distribution System
I. Introduction
This proposal for
operation and maintenance manual will be developed as a guide and system
familiarization hand book for the operation and M&E personnel of the HRCTB
, Location of the project.
This system- oriented
(O&M) instruction Manual is not intended to replace contract documents,
shop drawings, as-built drawings, or the equipment manufacturer's operating and
maintenance instructions, but is a supplement to those documents.
A system-oriented
operating Manual is a management tool. It helps communicate to each person
working in the HRCTB, the designer's intentions about how to operate the
systems under normal and emergency conditions. This manual is broken down into
separate sections for each Hotel, Office, and Car-Park space with its own table
of contents as outlined below.
Contained in this proposal
of O&M Manual is the following information:
II. FACILITIES/LOCATION
________________________________________
III. Scope of Work工作範圍
1. Space Location
(WHERE )
2. TRADE
A.
Mechanical , Electrical and Electronics
1). Electrical Power
_____________________________________________________________________
DRAFT(Not for construction,
Revised and updated required)
Training Manual PPC/ADSC
Electrical Power System
April 7th., 2014
_____________________________________________________________________
TABLE OF CONTENTS
Section Title Page
I PURPOSE AND SCOPE OF
MANUAL
A.
PURPOSE
B.
SCOPE
II LEGEND
III DESCRIPTION OF POWER
SYSTEM
A.
Arrangement
B.
22.8 KV primary switchgear "
"
C.
Main Transformers
D.
Low Voltage Switchgear "
" , " ", &
" ".
E.
Protective Relaying
F.
Metering and Operators Devices
G.
Power Monitoring System
H.
Main Panelboard
I.
Grounding System
IV OPERATION OF POWER SYSTEM
A.
Normal
Operation
B.
Abnormal Operation
C.
Parallel Operation
D.
Low Voltage Switchgear
E.
Relaying
F.
Drawout Air Circuit Breakers
G.
Main Panelboard
H.
Power Monitoring System
I.
Grounding System
V MAINTENANCE OF POWER SYSTEM
A.
22.8 KV Medium Voltage Switchgear
B.
2) Electrical Lighting
3). Electronics
a.
Fire Protection
b.
Security
c.
Telephone/ Data Processing /Telecommunication
d.
CCTV
e.
Energy Management
f.
BAS (Building Automation System)
g.
The others
1). HVAC
a.
Chillers
b.
Air Handling Units
c.
Fan coils
d.
Cooling Towers
e.
Piping
f.
Air ducts
g.
Control and monitoring systems
h.
The others
2). Plumbing
a.
Pumps
b.
Piping
c.
Devices
d.
Control and monitoring system
e.
The others
Project Name: As shown, (Not for Construction, Draft)
Re: M&E SYSTEM DATA
____________________________________________________
I.
Building Data DRAFT
A.
Building Type and Primary Functions:
B.
Location:
C.
General:
1.
Gross Area
2.
Net Occupied Area
3.
No. of Floors
II.
Lighting
A.
What are major area lighting levels and types?
Area Type Watts
FC Control
1.
Hotel
2.
Office
a.
Executive Offices
b.
General Offices
c.
Conference Rooms
d.
Corridors
e.
MER's
f.
Lobbies
g.
Toilets
h.
Exterior
i.
Parking
_______________________________________________________
Legend: TC - Time clock
LS- Local switching (How Local)
D - Dimmer
MH - Metal Halide
F
- Fluorescent
I
- Incandescent
MV - Mercury Vapor
HPS - High Pressure Sodium
______________________________________________________
B.
In general, what type of wall covering and what
colors are in major areas?
Area Wall Covering
& Color
Executive Offices
General Offices
Conference Rooms
Corridors
Lobbies
Parking Garage
C.
What type of ballasts are being used?
D.
What voltage are incandescent lamps rated for?
E.
What sequence of lighting controls is presently
used? That is, how many hours each day is major area lighted and what
"cleanup program " lighting is presently employed?
F.
Is interior lighting on the exterior of the
building separately controlled for possible shut off on bright days?
G.
Do fluorescent fixtures use reflective covers to
maximize light refraction? If so, are they maintained clean?
H.
Is lighting presently task oriented or modular?
I.
Is furniture integrated lighting presently
employed in the facility?
J.
Describe major lighting fixture types used.
(Watts, dimensions manufacturer, lightshield, voltage, etc.)
K.
What stair lighting methods and control are used?
L.
What decorative lighting can be reduced or
eliminated?
M.
Is exterior lighting under TC or photocell
control?
N.
Can exterior lighting be reduced or eliminated?
3.
Car-Park
III.
Power
A.
Obtain utility rates, billings and demand interval
for past year.
B.
Has a recent rate study been made to determine
whether or not the facility has the most efficient rate and meter arrangement?
C.
Is voltage regulation maintained within standard
limits? (+/- 10%)
D.
Does large refrigeration equipment utilize a
demand limiter?
E.
Is there a central plant? What is the power
factor? Does the utility rate schedule have low pf penalty or high pf incentive
clause?
F.
Is load shedding presently employed to conserve
energy and limit demand? If so, describe method.
G.
What major heavy loads are operated during peak
demand periods?
H.
Do mechanically refrigerated drinking fountains
remain on during non-working hours? (Manufactures estimate drinking fountains
operate on an average of 10 minutes each hour).
I.
Are elevators and escalators kept operating 24
hours a day?
J.
Are there electric kitchens on the premises? If
so, is it used during peak demand periods?
K.
Are there emergency generators in the facility? If
so, are they used during peak demand periods?
L.
When and what method of exercising and testing the
generators are used?
M.
Are major distribution transformers operating on
center tapes?
N.
What is the temperature in the transformer and
switchgear rooms?
O.
Are motor starter contacts maintained?
P.
Are motor sizes matched to equipment shaft sizes
to operate at the most efficient point?
Q.
Are loads balanced over all phases?
________________________________________________________________
R.
Load Data
1.
List estimated sizes of controllable loads (For
limiting or shedding) in kW.
a.
Exhaust and Intake fans
b.
Re-circulation fans
c.
HVAC compressor motors
d.
Chiller motors & pumps
e.
Type of chillers
f.
Hot water heaters
g.
Duct heaters
h.
Refrigeration
i.
Pool heaters
j.
Boilers
k.
Fluid pumps
l.
Heat pumps
m.
Furnaces
n.
Battery Charges
__________________________________________
Survey questionnaire for the Design of Electrical Systems
Note: Modify the following to suit the particular project for which
information is being sought.
Project Name: As shown above(Draft).
A.
GENERAL
1.
What are applicable Codes?
2.
Survey of existing utilities on and in vicinity of
site indicating size and location of electrical, telephone and miscellaneous
communications lines.
3.
Is there any requirement for submission of plans
and specifications for approval by municipal agencies?
4.
Are Design and specifications to be prepared on
local or foreign equipment? If local, obtain information on local equipment.
5.
Description and criteria of security, national
emergency and fall-out protection systems.
6.
Is the project site located in an earthquake zone?
What seismic rating is the zone?
B.
ELECTRIC UTILITY SERVICE
1.
Available service voltages:
Volts: Phase: Wire: Hz.:
2.
Available short circuit:
3.
Available service entrances? Indicate number,
types and locations.
4.
What is the experienced percentage fluctuation of
the Utility system voltage and frequency during normal operation?
5.
What is the experienced frequency and duration of
scheduled and non-scheduled power outages in the vicinity of the site.
6.
What is the frequency, duration and magnitude of
"brownouts" (Intentional Utility system voltage reduction)?
7.
What are the largest across-the-Line motors
acceptable to utility company?
8.
What is the Division of work between Utility and
building owner? Utility Co. back charges? (Describe).
9.
Overhead or secondary Utility service to site?
10. Primary and
secondary service metering and rate schedules for each.
11. Is billing
conjunctive (sum of instantaneous total maximum demand) or totalized (sum of
highest maximum demands)?
12. What is the
length of the period used to determine the demand?
13. What are
Utility Company requirements for transformer vaults, cables, metering,
approvals, shop drawings, others?
C.
TELEPHONE SYSTEM
1.
Is there a specific location or choice of
locations where service will enter the site?
2.
Is service to the site overhead or underground?
NOTE: USE PARAGRAPHS 3-7 IF LOCAL TELEPHONE COMPANY
IS PROVIDING SYSTEM:
3.
What is division of work between utility and owner
on incoming service?
4.
What are telephone company requirements regarding
service termination space and internal distribution.
5.
What is the minimum conduit-bending radius?
6.
Where will power be required? Normal or emergency?
7.
What special requirements does the owner have
regarding the telephone system?
NOTE: USE PARAGRAPHS 8-18,
WHERE PRIVATE SYSTEM WILL BE DESIGNED BY CONSULTING ENGINEERS.
8.
What type of service is available? Describe:
9.
What type of signaling will be used? Describe:
10.
What type and gauge of cable will be terminated on
the Main Distribution Frame (MDF)?
11.
What type of central Office (CO) side MDF
protection is required? Describe:
12.
What type of trunk service is available? 4-wire; 2-wire; Other; Describe.
13.
What is the maximum loop resistance including
station or key equipment?
14.
Are repeaters required?
15.
Will precise tone multi-frequency dialing be
accommodated by the Central Office? Yes( ), No ( ), If yes, what standards
should be used?
16.
What is central office and national system data
transmission rate in baud or bits per second (bps)?
17.
How do you want the traffic and grade of service
calculations presented?
18.
Other than BSP (Bell System Practices) do you have
any other standards or regulations we should be aware of?
D.
GENERAL REQUIREMENTS
1.
Systems and Equipment Criteria
a.
Lighting:
U.S. Illuminating Engineering Society (IES): U.S. Federal Energy
Administration (FEA) ; British Standards ; Other ; describe:
b.
Lightning Protection: U.S. National Fire
Protection Association (NFPA) (); British Standards (); Other (); Describe:
c.
Equipment:
U.S. with Underwriters' Label (); Other (); describe:
E.
BUILDING UTILIZATION VOLTAGES
1. Volts, Phase, Wire,
Hz. For: Hotel
2. Volts, Phase, Wire,
Hz. For: Office
3. Volts, Phase, Wire,
Hz. For: Car Park
F.
STANDBY EMERGENCY GENERATOR
1.
The following is a list of systems and equipment
generally placed on emergency standby power. Please review and modify if
required.
a.
Exit lighting
b.
Partial - corridor, stair and selected area
lighting
c.
Elevators (on selective basis- one at a time)
d.
Refrigerators
e.
Fire pumps
f.
Sewage and sump pumps
g.
Telephone and communications system
h.
Alarm systems
i.
Security systems
j.
Control air compressors
k.
Generator room appurtenances
G.
OFFICE
FOLLR POWER DISTRIBUTION
1.
Is the flexibility of an under-floor distribution
system required?
2.
What areas or load concentrations exist requiring
special provisions (Such as special guestrooms, VIP Room, etc.).
H. SPECIAL SYSTEMS FOR POSSIBLE
INCLUSION
1.
Equipotential Ground System
2.
UPS
3.
Isolated Power System
4.
Manual Fire Alarm System
5.
Smoke and Fire Detection Systems
6.
Lightning Protection System
7.
Grounding System
8.
Security and Watch Patrol System
9.
CCTV (Closed Circuit Television)
10. Intercommunication
System
11. Public Address
System
12. Sound System
13. Television
System
14. Radio System
15. Satellite
System
16. Helicopter
related
H.
More will
be listed as per owner’s request- Philip Pai-Pin Chen.
Nyseasia us; nyseasia NY
Nyseasia worldwide.
May 23, 2014
ReplyDeletePhilip Pai-Pin Chen.
I. Peace, Good days & Happiness forever Local & Worldwide.
Mission Critical & Essential Worldwide.
Nyseasiaworld.com, FaceCritical.com
II. Green Energy & Power Promotion Task Force, Missions 2014-2024
III. Burton Hillis said:
I'm not convinced that the world is in any worse than it ever was. It's just that in this age of almost instantaneous communication, we bear the weight of problems our forefathers only read about after they were solved.
IV. Heavy rains continued in the last five days, some lower area covered by water or flood, so far, still under control.-Thank you so much.
V. Less is more, more or less.
1. Less burning, less combustion of materials- coals, fossil fuels, etc.
2. More solar, wind, natural energy and power conversion, transformation.
3. Build & Design ,Electric Drive systems:
(1).Mass Transportation Systems, Super High Speed Rails,
(200-250 miles per hour), across USA, Canada, Central & South America.
(2). Electric buses, cars, bikes.
PowerStationSolar.com, PowerStationWind.com, BatteryAssociates.com.
Highly appreciated.
VI. Bulgarian Proverb:
You are permitted in time of great danger to walk with the devil until you have crossed the bridge.
VII. Peace Priority Local & Worldwide
Anonymous:
It is better to know nothing than to learn nothing.
Good days & Happiness forever local & Worldwide.-Philip Pai-Pin Chen.
VIII. More to be listed-Thanks.
Nyseasia us; nyseasia NY
Nyseasia worldwide.
nyseasiaworld.com