Friday, September 26, 2014

Peace and good days worldwide. nice weekend worldwide; Thank you so much. Philip Pai-Pin Chen,ieee.mobi, leee.mobi, SyskaHennessy.mobi; JarosBaumBolles.mobi,TaiwanChina.mobi, TaiwanChina.us, Professionism since 0829,1983, Earlier and later. Thanks. 09272014

September 27, 2014
Philip Pai-Pin Chen.

Peace and good days Worldwide.
Back on line-Thanks.
陳柏彬;
陳柏彬;工程師.com; 電機技師.com;中台房地產.com; 中台房地產.tw;
Mission Critical, Broad, NY, USA Worldwide; paipinchen.com, 09272014

Keys for the days.
I.                   Key one of three.
Hubert H. Humphrey, The Former Vise-President of United States Of America, 1965-1969, Said:
They [they good old days] were never that good, believe me. The good new days are today, and better days are coming tomorrow. Our greatest songs are still unsung.

II.                Key two of three.
Old proverb said:
The person who pursues revenge should dig two graves.

III.             Key three of three.
Dwight D. Eisenhower said:
 People want peace so badly that governments ought to get out of their way and let them have it.

Draft.
Revised and updated required.
Attention please:
 The materials shown not for Construction and any other any purposes.
Please contact me should you have your concerns. Highly appreciated.
Back on line-Thanks.-Philip Pai-Pin Chen.
Random for today.
Field one :
One of two for today and coming days.
Electrical and associated.
1.      Capacity of Generators.
A.Small sizes.
0.5 kw; one kw, 1.5 kw, 3kw,5kw, 7.5kw, 10kw,15 kw, 20kw, 25kw, 30 kw;45kw, 50kw,75kw, 90kw, 100kw.125kw and so on as per shown here and coming days.
B. Medium sizes.
200kw, 250kw, 300kw, 450kw, 500kw, 600kw, 800kw.
C. Larger sizes.
1000kw, 1250kw, 150kw, 1750kw, 2000kw, 2500kw, 3000kw.
D. Large sizes.
5000kw-5mw; 7500kw, 7.5mw, 10mw, 20 mw, 30mw, 50mw, 75mw.

Field two.
Business and marketing.

Two  of two for today and coming days.


September 27th., 2014
Philip Pai-Pin Chen
Peace and god days worldwide.

Thank you very much.
NYSEASIAWORLD Local & Worldwide.
Nyseasiaworld worldwide.

Please note: The materials shown below Not for any purposes and also Not for Construction.
Please contact me or the head office in NYC, New York, USA should you have any suggestions or planning for your coming projects. –Thanks. Philip Pai-Pin Chen.
Draft.
Revised and updated required.
CONTRACT CHECKLIST
This checklist was reviewed on September 23, 2014   , at   N/A    , between Mr. /Ms. N/A    Of  “NYSEASIAWORLD.com & Associates “ and Mr. /Ms.   N/A   Of   “Specific projects of Lands and Areas Developers “   , and will be used as the basis of the Agreement between both parties.
When agreed to by both parties, this contractlist can be attached as a rider to the Agreement; and therefore, be a part of the Agreement.
1.       Project Description
1.1   Type of Project
1.2   New and/or Existing Building(s)
1.3   Type of Construction (i.e., steel and concrete, concrete, etc.)
1.4   Number of Buildings
1.5   Base Building Core and Shell and/or Tenant Work
1.6   Gross Square Feet Areas of Building(s) and Site (Acres)
Day one, contract checklist, nyseasiaworld, 09222014.
P1 of 13 (continued).

1.7   Location (address if available) City, State, Country
1.8   Estimated cost if established
1.9   method of preparing documents and bidding (i.e.,Fast track, multiple prime contract, etc.)
                                 Work        Additional      Comments
2. Scope of Services               Included      Engineering      
                                              Services
a. Schematic Design Phase*
(1) Studies-Engineer will study
      the following alternative
      systems including advantages,
      disadvantages, budget cost
      and recommendations.
-HVAC (INCLUDING CENTRAL PLANTS) (LIST)
-ELECTRICAL (List)
-SANTARY (List)
-VERTICAL TRANSPORTATION (List)
-FIRE AND LIFE SAFETY (List)
-SECURITY (List)
-COMMUNICATIONS (i.e.,data, etc.) (List)
-Other
Notes:
(a)     Recommendations for further studies
in subsequent studies in subsequent
phases of project.
(2)    Survey of existing facilities and conditions and report of findings.
(3)    verification of accuracy of drawings or other information furnished by owner.
(4)    Design Criteria including applicable codes and standards, and systems descriptions.
(5)    Space conditions and weights for M/E and other applicable trades equipment.
(6)    Outline Specifications.
(7)    System Flow and/or Riser Diagrams, block layouts of M/E and major spaces.
Day two, contract checklist, nyseasiaworld, 09222014.
P2 of 13 (continued).



(8)    Part or full typical floor layout for:
-HVAC
-ELECTRICAL
-SANITARY

-FIRE PROTECTION
(9)    Major equipment sizing.
(10) Discussions and confirmation
with applicable public agencies
and utility companies concerning
project and services.
Note:  This should be specifically
discussed with client since on some
projects (especially in the Schematic
Design Phase ) we are directed not
to contact anyone regarding the
project.
(11) Preparations of estimated
    construction costs on a square foot
    basis.
   (Note:  This may be provided by Engineer,
Construction Manager, General Contractor
or Cost Consultant. )
b.       Design Development Phase (Based on
   Approved Schematic Design Phase) *
(1)    Additional Studies for:
-HVAC (List)
-Electrical (List)
-Sanitary (List)
-Vertical Transportation (List)
-Automation (List)
-Fire and Life Safety (List)
-Security (List)
-Communications (List)
-Other (List)

Day three, contract checklist, nyseasiaworld, 09222014.
P3 of 13 (continued).


(2)    Outline Specifications (if not furnished
during Schematic Phase ) or first pass
using final specifications. If final
specifications are to be used, verify format.
(3)    Updated drawings confirming space
conditions, weights, equipment and system
sizing and selection.
(4)    Updated Design Criteria.
(5)    Updated utility information.
(6)    Updated estimated construction costs.
(Note: This may be provided by Engineer,
Construction Manager, General Contractor
or Cost Estimator.)
c.        CONSTRUCTION DOCUMENT PHASE
(Based on approved design development Phase)*
(1)    Additional Studies for:
- HVAC (List)
- Electrical (List)
- Sanitary (List)
- Vertical Transportation (List)
- Automation (list)
- Fire and Life Safety (List)
- Security (list)
- Communications (List)
-Other (List)
(2)    Final Specifications and verify format.
   (Unless already established in Design
   Development Phase)
(3)    Final Drawings - verify size of drawings.
(4)    Verify if separate Drawings and/or
Specifications are required for :
n  Tenant Areas
n  Special System (i.e., Security, etc.)

Day four, contract checklist, nyseasiaworld, 09222014.
P4 of 13 (continued).



(5)    Filing of documents with authorities having
jurisdiction. Verify scope (i.e., preparing
submissions or actually filing).
d.       Bidding and Construction Phase*
(1)    Review and recommend list of bidders.
(2)    Pre and Post bid meetings with Contractors.
(3)    Analyses of Bid and contractors proposed
substitutions prior to award of Contract
(Where allowed by Specifications).
       Note:  If substitutions affect design,
       system performance and intent, this
       should be considered as additional
       Engineering Services. This would
       include time for the analyses and
       implementation, if the substitution(s)
       are accepted by client.
(4)    Review of Shop Drawings and Samples.
Note:  Engineer will include in Final
specification items required to be submitted
for review. If other items are submitted and
require review, they will be considered as
additional Engineering Services.
(5)    Review of Contractor prepared coordination
drawings.
(6)    Preparation of Change Orders, Other than
owner initiated.
(7)    Review of Contractors application for
payments for Contract Work and for
authorized Change Orders.
(8)    Preparation of As-Built Drawings,
    or Review of Contractor prepared
As-Built Drawings.
Day five, contract checklist, nyseasiaworld, 09222014.
P5 of 13 (continued).




(9)    Field Observation
(a)     Periodic - fixed number.
(b)    On Call.
(c)     Full Time and determines
number of personnel.
(10) Attendance at Field Meetings and
 establish frequency.
(11) Punch Lists and Final Acceptance.
(12) Witnessing Factory Tests.
*Note:  Some Government Agencies
require very specific work to be performed
under the various phases of Services
(i.e., submissions based on a % of completion).
Where applicable, they must govern.
3.       Special Services
  The following Services are not included as
  part of Basic Services; and therefore, not
  included in Basic Fee.
a.        programming and special analyses
(i. e., space relationship scheduling, etc.).
b.       Assisting in the preparation of application for
government grants or financing for project.
c.        Environmental Impact Studies and analyses
   and assistance in obtaining approval from
   authorities having jurisdiction.
d.       Services related to future facilities.
e.        Preparing separate Construction Documents
   for Alternates. Where fee basis is % of Construction
   Costs, this would be only applicable for work not
   constructed. Where project is Lump Sum or Time
   Card to Upset, all alternates whether constructed or
   Not is a Special service.

Day six, contract checklist, nyseasiaworld, 09222014.
P6 of 13 (continued).



f.        Prepare Change Orders to reflect changes initiated
   by Owner. Where fee basis is % of Construction
   Costs, This would be applicable for work not
   contructed. If work is constructed, the preparation
   of the Change Order is still a Special Service and
   the fee should be adjusted based on % of
   construction cost to cover other aspects of work
(i. e., Coordination, Shop Drawings, field
Observations, etc.).
Where project is Lump Sum, or Time Card to
Upset, preparation of Change Orders whether
constructed or not is a special Service.
g. Services in connection with evaluating
  substitutions proposed by Contractors after
  award of contract.
h.       Making revisions to Drawings and/or
   Specifications related to the substitutions.
i.         Providing coordination of work performed
   by separate contractors.
j.         providing quantity surveys and detailed
Construction Cost Estimates.
k.       Providing services in connection with the
work of a contruction manager or other
 consultants retained by Owner.
l.         Providing services related to the start-up of M/E
systems.
m.     Preparing to serve or serving as an expert witness
   in connection with any public hearing, arbitration
   or legal proceeding.
n.       Preparing Operations and maintenance Manuals.
o.       Analyzing maintenance and operating costs for
Project or portion of project.

Day seven, contract checklist, nyseasiaworld, 09222014.
P7 of 13 (continued).



p.       Providing training of personnel for operations
and Maintenance.
q.       Providing consultation services after completion
of Construction phase and final acceptance
(including follow-up field observation, preparing
follow-up punch lists, etc.).
r.         Preparing energy analysis subsequent to occupancy.
s.        Designing of Mock-ups, Samples and Demonstration
Models including their construction and demolition
costs.
t.         Services of Special Consultants For:
(1)    Acoustics
(2)    water Treatment
(3)    Cost Estimating
(4)    Laboratory Tests
(5)    Electrical Tests (Electromagnetic Interference, etc.)
(6)    Structural
(7)    Architectural
(8)    Other
u.       All reimbursable costs, including travel time
for the above
(or any other additional Special Services).
4.       Field Services
The services described in Paragraphs 2 and 3 will
cover the following fields:
Note:  Where Special systems are to be included,
they should be reviewed with the Engineering
Policy Committee.
a.        Mechanical Engineering
(1) Air conditioning           
(2)    Heating
(3)    Ventilating
Day eight, contract checklist, nyseasiaworld, 09222014.
P8 of 13 (continued).

(4)    Boiler plant
(5)    Refrigeration Plant
(6)    Site Distribution piping for:
(7)    Special Systems
Note:  The inclusion of the following
will either increase the basic fee or
treated as pecial Services.
-Solar Energy
-Energy Storage ( ice, Chilled Water, hot water, etc.)
-Heat Recovery
-Process Piping
-Automation and Control ( can be provided under
 Automated monitoring and Control Services)
 -Design for Atriums, Malls or other special areas.
 Note: Requirements for special smoke control systems.
 -Humidity Control
 -Clean Room Laminar Flow Systems ( Class to be determined)
 -Other

b.       Electrical Engineering
(1)    Incoming Service
(2)    Interior Distribution
(3)    Telephone Conduit System
(4)    Building Standard Lighting
(5)    Building Standard Lighting Control
(6)    Motor Control
(7)    Clock System
(8)    Fire Alarm Systems*
(9)    Master Antenna Systems*
(10) Grounding System- 25 ohms to Ground
(11) Normal Utility Metering
(12) Emergency power System
(13) Underfloor Raceway System Design
(14) Pipe Beat Tracing
(15) Snow Melting

Day nine, contract checklist, nyseasiaworld, 09222014.
P9 of 13 (continued).



(16) Nurses Call System
(17) Patient Headwall Systems
(18) Equipotential Grounding Systems
(19) Special Systems
    Note:  The inclusion of the following
    will either increase the Basic Fee or be
    treated as Special Services.
 -Site Electrical Distribution
 -Site Telephone Distribution
 -Special Area Lighting (Define)
 -Special Area Lighting Control
(i. e., Dimming,Etc.) ( Define)
 -Data Communications Systems*
 -Telephone Systems*
 -Security Systems*
 -Special Signal & Alarm Systens*
 -Halon Systems (Wiring)
 -Satellite Earth Station Provisions
 -CCTV Systems*
 -Sound & Paging Systems*
 -Door Alarm Systems*
 -Grounding Systems of Less than 24 ohms to Ground
 -Vehicular Access Control
 -Intercom Systems*
 -UPS Systems
 -Modular Wiring Systems
 -Electrical Submetering Systems
 -EMI Shielding
 -Computer Rooms
 -Kitchens
 -Audio/Visual Work (Wiring)
 -Other

Day ten, contract checklist, nyseasiaworld, 09222014.
P10 of 13 (continued).



* CAN BE PROVIDED UNDER AUTOMATED
  MONITORING AND CONTROL SERVICES.
c.        Sanitary Engineering
(1)    Sanitary drainage and Vent
(2)    Storm Water Drainage
(3)    Domestic Hot & Cold water
(4)    Fire Standpipe
(5)    Hospital or Laboratory Medical Gas
Systems ( Oxygen, Nitrous Oxide,
Compressed Air)
(6)    Hospital or Laboratory Vacuum Air
(7)    Hospital or Laboratory Nitrogen (for power Operated Tools)
(8)    Hospital or Laboratory Acid Waste
(9)    Hospital or Laboratory Compressed Air
(10) Hospital or Laboratory Vacuum Air
(11) Special Systems
Note:  The inclusion of the following will either increase the Basic Fee or
be treated as Special Services.
-Gas
-Kitchen
-Laundry
-Decorative Fountains
-Swimming Pool
-Spa Pool
-Water Softening
-Water Treatment (Distilled, Deionized, Reverse Osmosis)
-Central Chilled Drinking Water
-Non-Potable Water (For Flushing Purposes)
-Waste Pulping
-Vacuum Cleaning
-Soap Dispensing
-Lawn Irrigation
Day eleven, contract checklist, nyseasiaworld, 09222014.
P11 of 13 (continued).



-Site Sanitary Sewers
-Site Storm Water Sewers
-Site Gas
-Site Domestic Water
-Site Fire
-Gasoline Dispensing
-Hospital or Laboratory Infectious Waste
-Hospital or Laboratory Infectious Waste
-Hospital or Laboratory Oral Vacuum
- Hospital or Laboratory Waste Anesthetic Gas
- Hospital or Laboratory Helium
 -Hospital or Laboratory Carbon Dioxide
 -Hospital or Laboratory Vacuum Cleaning
 -Other
d.       Fire Protection Systems
(1)    Sprinkler Systems
(2)    Fire Protection Systems
(3)    Halon Systems
(4)    Other
e.        Transportation Systems
(1)    Elevators
(2)    Escalators
(3)    Pneumatic Tubes
(4)    vertical and Horizontal Conveyors
(5)    Moving Sidewalks
(6)    stage Equipment
f.        Automated Monitoring and Control
( if not included under HVAC and
 Electrical Engineering)
(1)    Automation and controls
(2)    Fire alarm systems
(3)    Master Antenna Systems
(4)    Data Communication Systems

Day twelve, contract checklist, nyseasiaworld, 09222014.
P12 of 13 (continued).


(5)    Telephone Systems (PBX)
(6)    Security System
(7)    Special Signal Alarm Systems
(8)    CCTV Systems
(9)    Sound & Paging Systems
(10) Sound Masking Systems
(11) Door Alarms
(12) Intercom Systems
g.       Energy Management
h.       Facilities Management
i.         Other
Filed. Ieeemobippcpe at Gmail dotcom, paipinchen.com;nyseasia@gmail.com;09222014.
Day thirteen, contract checklist; nyseasiaworld.com, since May 7th. 2014
P13 of 13 (end).
Filed. ieeemobippcpe@gmail.com;nyseasia@gmail.com;nyseasia@hotmail.com;paipinchen.com,09272014.




No comments:

Post a Comment